What: Weather permitting, the Georgia Department of Transportation (Georgia DOT) construction partners will temporarily close interstate lanes at the locations below for the I-285/I-20 East Interchange project. The project will reconstruct the interstate system-to system ramps at the I-285/I-20 East Interchange and add a combination of collector distributor, or connecting lanes, and auxiliary lanes along I-20 east of the interchange and I-285 north of the interchange
Where/When:
I-20 at the I-285 Interchange (MM 67.3)
-
Saturday, June 29, through Tuesday, July 2, from 11 p.m. to 5 a.m. (Nightly)-
Pacing operation on I-20, both eastbound and westbound
I-20 from the westbound ramp to I-285 northbound (Exit 67B)
-
Saturday, June 29, through Tuesday, July 2, from 11 p.m. to 5 a.m. (Nightly)-
Pacing operation on the I-20 westbound ramp
I-20 from the westbound ramp to I-285 northbound (Exit 67B)
-
Saturday, June 29, through Tuesday, July 2, from 9 p.m. to 5 a.m. (Nightly)-
Single left lane and left shoulder closure on the I-20 westbound ramps
I-20 entrance ramps from I-285 northbound starting at the Rainbow Drive overpass (MM 46.8)
-
Monday, July 1, and Tuesday, July 2, from 1 p.m. until 2:30 p.m. (Daily)
Pacing operation on I-20 eastbound, traffic will be held for up to five minutes
I-20 from Columbia Drive (MM 66.8) to Panola Road (MM 71.3)
-
Monday, July 1, and Tuesday, July 2, from 1 p.m. until 2:30 p.m. (Daily)
Pacing operation on I-20 eastbound, traffic will be held for up to five minutes
I-20 entrance ramps at Panola Road (MM 71.6) and Wesley Chapel Road (MM 69.5)
-
Monday, July 1, and Tuesday, July 2, from 1 p.m. until 3 p.m. (Daily)
Pacing operation on I-20 westbound, traffic will be held for up to five minutes
Hillandale Drive eastbound from the Salem Bible Church to the Emory Hillandale Hospital
-
Monday, July 1, and Wednesday, July 3, from 9 a.m. to 3 p.m. (Daily)
Flagging operation
|
Activity
|
Start Date
|
End Date
|
Times
|
I-20 Westbound
|
|
Pacing operation
|
06/29/24
|
7/2/24
|
11 p.m. - 5.a.m.
|
-
I-20 from the westbound ramp to I-285 northbound
|
Pacing operation
|
06/29/24
|
7/2/24
|
11 p.m. - 5 a.m.
|
-
I-20 from the westbound ramp to I-285 northbound
|
Single left lane and left shoulder closure
|
06/29/24
|
7/2/24
|
9 p.m. - 5 a.m.
|
-
Entrance ramps at Panola Road and Wesley Chapel Road
|
Traffic pacing operation
|
7/1/24
|
7/2/24
|
1 p.m. - 3 p.m.
|
I-20 Eastbound
|
|
Traffic pacing operation
|
06/29/24
|
7/2/24
|
11 p.m. - 5.a.m.
|
-
Entrance ramps from I-285 northbound starting at Rainbow Drive
|
Traffic pacing operation
|
7/1/24
|
7/2/24
|
1 p.m. - 2:30 p.m.
|
-
From Columbia Drive to Panola road
|
Traffic pacing operation
|
7/1/24
|
7/2/24
|
1 p.m. - 2:30 p.m.
|
Hillandale Drive Eastbound
|
|
|
|
|
-
From the Salem Bible Church to the Emory Hillandale Hospital
|
Flagging Operation
|
7/1/24
|
7/3/24
|
9 a.m. - 3 p.m.
|
NOTE: Holiday work restrictions will be in place from Wednesday, July 3, 2024, at 12 p.m. through Friday, July 5, 2024, at 10 p.m. No road closures or work that restricts or interferes with traffic will be conducted during this time frame.
|
|
Advisory: Exact time may change due to weather conditions. Motorists are advised to expect delays, exercise caution, and reduce their speed while traveling through work zones, stay alert, and watch for workers. Before heading out, get real-time information on work status and traffic conditions. Call 511, visit 511ga.org, or download the Georgia 511 app.
|
|
|