11/21/2024 | Press release | Distributed by Public on 11/21/2024 13:48
Anderson County
Palestine crews will be repairing potholes at various locations throughout the county.
Anderson County construction projects updates:
US 175 Widening Project
The contractor is scheduled to continue working on the new westbound bridge and roadway elements, including pavement and ditch work on the eastbound and westbound sides. FM 1892 is now closed, and traffic is being detoured to CR 307. Motorists should use caution when traveling through the project. Traffic switch is expected at the north end of the project. Expect lane closures and delays. The speed limit is reduced throughout the project limits. Project consists of expansion to a four-lane roadway with new bridges across the Neches River.
US 79 Truck Parking Area
The contractor is awaiting final acceptance. Operations will be in the right of way, but motorists should use caution when traveling through the area. The project includes concrete curb and gutter, earthwork, and drainage improvements.
Gus Engeling Texas Parks and Wildlife
The contractor is awaiting final acceptance. Operations are off public roadways. The project includes surface treatment, pavement striping, and drainage improvements.
----------------------------------------/p>
Cherokee County
Jacksonville and Rusk crews will be working in the maintenance yards next week.
Cherokee County construction projects updates:
SH 204
The contractor is scheduled to place hot mix asphalt for the driveways, culvert extensions, place topsoil, and permanent seeding. Crews will also reinstall storm water drainage on the west end of the project. Crews are also expected to excavate and haul material to the east end of the project. Traffic delays are expected due to lane closures. The project consists of adding a super-two highway section./p>
US 175 Widening Project
The contractor is working on the westbound side of the road behind the traffic barrier. The east end of the CR 3407 (Dip Road) intersection closed Monday, Oct. 28. Drivers should use the west end of CR 3407 to access U.S. 175. Crews are setting bridge beams, and one-way traffic control is in place. The contractor is also clearing utility items. Drivers should watch for large dirt-moving equipment and a traffic switch in the construction area. The speed limit is reduced to 55 mph throughout the project. This project will expand U.S. 175 to a four-lane road with new bridges, grading, asphalt paving, drainage, pavement markings, and signs.
US 69 Safety Improvement
The contractor is scheduled to install the mow strip in the medians along US 69. They will also install the anchors for the new cable barrier. Lane closures are anticipated. The project consists of safety improvements consisting of the installation of a median cable barrier.
FM 2339 - SH 110
The contractor is scheduled to work on the new retaining wall. Crews will also be clearing the area for the permanent retaining wall. No lane closures are anticipated. This project is a change order to a bridge preventative maintenance project that consists of installing a temporary soil nail wall and a permanent soldier pile retaining wall to address slope failure on SH 110.
----------------------------------------
Gregg County
This week, Longview Maintenance is scheduled to work off the roadway on FM 2275 at Graystone Road. Crews will be cutting down the right-of-way grade to help improve sight distance for oncoming traffic. Motorists should watch for workers in the area.
Gregg County construction projects updates:
SH 135 - Kilgore Traffic Circle
This project involves rebuilding the traffic circle and the entire width of the roadway up to the Rusk County line. Crews will demolish the west side of the road, which includes removing the old concrete, rebuilding the foundation, installing new concrete pavement, adding storm sewers, and completing lighting and striping. Two-way traffic is now open south of the traffic circle. The contractor is working on storm sewers and paving at the circle.
FM 2206/Harrison Road Phase 1
This project will widen a two-lane road to four lanes with a center turn lane. The work includes adding drainage structures, a flexible base, curbs and gutters, sidewalks, asphalt paving, and pavement markings. Crews will install hot mix asphalt and striping.
FM 2206/Harrison Road Phase 2
This project will widen a two-lane road to four lanes with a center turn lane. The work includes adding drainage structures, a flexible base, curbs and gutters, sidewalks, asphalt paving, and pavement markings. Crews will install hot mix asphalt and striping.
High Street Bridge over UP Railroad
This project will replace the High Street bridge over the UP railroad. High Street is reduced to two lanes - one northbound and one southbound. Crews will build one half of the bridge at a time and are working on retaining walls and the new bridge structure. Drivers should expect delays.
----------------------------------------
Henderson County
This week crews will be performing pothole and edge repairs at various locations throughout the county. Crews will also perform sign maintenance, herbicide application, and sweeping throughout the county. This work will only be done on Monday and Tuesday.
Henderson County construction projects updates:
SH 198 Bridge Project
The contractor is waiting for final vegetation to be established. Drivers should be ready for lane closures and delays. The speed limit is reduced to 50 mph throughout the project. The work includes replacing bridges and approaches, grading, structures, base and surface work, retaining walls, curbs and gutters, fencing, and striping.
FM 316 Rehabilitation
The contractor is working on punch list items and awaiting final vegetation establishment. Motorists should use caution when traveling through the project and expect lane closures and delays. The project includes pavement reconstruction, structures, pavement markings and signs.
FM 315 Rehabilitation
The contractor is working on punch list items. Motorists should use caution when traveling through the project and expect lane closures with delays. The project includes pavement reconstruction, structures, pavement markings and signs.
BUS 19 Sidewalks
Sidewalk construction is underway and will continue this week. Motorists should use caution when traveling through the project and expect lane closures and delays. This project includes sidewalk and pedestrian lane improvements.
----------------------------------------
Rusk County
Rusk County construction projects updates:
US 84 - FM 225 East to CR 3155
This project consists of reconstructing US 84, extended structures, hot mix asphalt surface, new signs, and striping. Crews will be extending cross culverts. Motorists should expect delays.
FM 3231 - Subgrade and Seal coat
This project consists of reconstructing FM 3231 completely. Work includes widening and re-laying subgrade, flex base material, and seal coat. Driveway culverts will be upgraded along with new signs and striping. The contractor is scheduled to process the base material in the main lanes. Expect lane closures with flaggers and a pilot car controlling traffic.
SH 315
This project consists of widening pavement edges and installing a four-foot space between the traffic lanes to separate opposing traffic for safety. Work will also include adding a passing lane in each direction of travel. The entire surface will be milled, and new hot mix will be placed for the final surface. Project also includes replacing some driveway pipes, metal beam guard fence, and striping. No work is scheduled this week.
FM 2658
This project consists of reconstructing FM 2658 completely, from CR 344 to FM 1251. Work includes a new guard fence, treating subgrade, base material, seal coat, and striping. The contractor is scheduled to mill off old asphalt and mix subgrade on the south end of the project. This will be a one lane setup with flaggers and a pilot car controlling traffic.
US 79 Rehabilitation
This project consists of rehabilitation of US 79 consisting of pavement repair, seal coat, asphalt surface, driveway culverts, and pavement markings. This week, the contractor is scheduled to clear the right of way. Motorists should expect delays with flaggers controlling traffic.
US 79 N
This project consists of repairing slope failure in the TxDOT right of way. The site will be excavated, and a new embankment will be placed. This week, the contractor will be placing the new embankment. Most of the work will be off of the roadway. Motorists should expect shoulder closures and trucks entering the highway.
----------------------------------------
Smith County
This week, Tyler Maintenance will have crews patching problem areas at various locations throughout the county. This will be a mobile operation. Another crew is scheduled to remove right of way encroachments. Another crew will be cleaning stockpile locations. Traffic control will resume after the Thanksgiving holidays.
Smith County construction projects updates:
Tyler State Park Bridge and Resurfacing Project
The contractor is pending the installation of a concrete flume with stone at the roadway runoff points. When complete, the contractor will then remove erosion control. This project consists of the construction of a new bridge and parking areas.
US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)
The contractor has no work scheduled this week. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at FM 2813 intersection.
SH 31 Safety Improvement
The project consists of safety improvements consisting of the installation of a median cable barrier.
SL 323 Overlay on Existing Roadway
The contractor is scheduled to perform permanent striping. Lane closures are anticipated. This project consists of overlaying existing roadway with new asphalt.
I-20 Frontage Road at SH 155
The contractor has no work scheduled this week. No lane closures or delays are expected. Project consists of resurfacing the roadway, pavement markings, signage, and illumination.
I-20 Mill and Inlay
The contractor has no work scheduled this week. Project consists of an overlay with new surface, planing, shoulder texturing, and pavement markings.
Legacy Trails Extension
The contractor is scheduled to finish pouring concrete for the parking lot in Stewart Park. They will also place riprap and construct the sidewalk and curb. Lane closures are possible on southbound Frankston Hwy. This project consists of a hike and bike trail development that includes construction of a 12-foot wide shared-use paths.
FM 2493 Widen Non-Freeway
The contractor has no work scheduled this week. No lane closures are in place. The project consists of widening the existing roadway.
County Bridge Replacements
The contractor has completed constructing drilled shafts and will begin the abutments soon. The bridge will be closed for the duration of construction. Project consists of replacing the existing bridges and approaches.
SH 110 Preventative Maintenance
The contractor has no work scheduled this week. No lane closures are anticipated. The project consists of preventative maintenance including planning, overlay, and pavement markings.
SH 110 Traffic Signals
The contractor has no work scheduled this week. This project consists of adding traffic signals to SH 110 and Loop 49 ramps and overlay operations.
I-20 Mill and Inlay at SH 135
The contractor is scheduled to clean and seal bridge joints and work on the entrance and exit ramps. They are also expected to begin permanent striping. Lane closures are anticipated. Project consists of an overlay with a new surface, asphalt concrete pavement, planing, shoulder texturing, and pavement markings.
FM 16 Widening and Realignment
The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. A major traffic shift is currently in place through town. Traffic will be two lanes during this phase of construction. Crews will also be working west of Lindale High School, hauling in embankment materials. They will also work on tying in the proposed roadway into the newly constructed bridge. Motorists are urged to drive with caution and expect delays.
---------------------------------------
Van Zandt County
Crews are scheduled to repair potholes at various locations. A second crew will be organizing stockpiles and moving materials as needed.
Van Zandt County construction projects updates:
SH 19 Super Two Widening & Overlay (North of US 80)
The project consists of construction of a super two lane widening. The work includes grading the surface, base repair, new asphalt surface, signage, and striping. Major items of work have been completed.
I-20 Frontage Roads West of FM 314 and East of FM 47
This project is for roadway restoration consisting of treating the existing surface, flex base, prime coat, metal beam guard fence, signage, and pavement markings. Work is in progress west of FM 314 and east of FM 47. Major items of work have been completed.
CR 1102 Bridge Replacement
This project is for the construction of a bridge replacement consisting of replacing bridge and approaches, grading, base and surface, and guard fence installation. Major items of work have been completed.
FM 17, FM 47, and FM 859 Bridge Replacement
This project is for the construction of a new bridge and approaches, grading, base and surface, and metal beam guard fence installation. The project will begin with the replacement of FM 859 & FM 47 bridges the last week of November. Motorists should expect work zone speed limit reductions and shoulder width reductions on the I-20 main lanes. Motorists should also expect work zone speed limit reductions and shoulder width reductions on the I-20 frontage roads. The bridge at FM 859 is open. FM 859 north of I-20 now has access to the bridge. FM 859 south of I-20 is closed and detours are in place. Motorists should pay attention and travel with caution in the area.
FM 1255 Rehabilitate Existing Roadway
This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, rework base material, cement treatment, flex base, resurfacing intersections & driveways, extending cross structures, signs, and pavement markings. The project will be completed under traffic. Subgrade rehabilitation will be completed in one-mile segments. Crews are scheduled to remove trees, work on cross culverts, and ditch grading over the next several weeks. Lane closures and speed zone reductions are expected. Motorists should expect delays.
SH 64 at I-20 and SH 155 at I-20 Traffic Signal Install
This project is for the construction and installation of traffic control devices including pedestrian signals. The SH 64 intersection striping layout has been completed. SH 155 intersection signals are complete and functioning. The frontage roads between SH 155 and Lawhorn Ave. will be switched from two-way to one-way only travel. Lane closures and speed zone reductions are expected. Motorists should expect delays.
SH 243 Traffic Signal Install
This project is for the construction and installation of traffic control devices including pedestrian signals. Major items of work have been completed.
I-20 WB Exit Ramp at SH 19
This project consists of ramp improvements. Crews have initiated construction on the drainage structures and frontage road alignment. Crews continue to haul in large amounts of dirt. Lane closures and traffic shifts are expected. Motorists should expect delays.
FM 1651 Rehabilitate Existing Roadway-Tony
Construction is on-going for cross structures, driveways, and right-of-way clearing. This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, base work, cement treatment, flex base, resurfacing intersections & driveways, extending cross structures, signs, and striping. The project will be completed under traffic. Subgrade rehabilitation will be completed in approximate one-mile segments. Lane closures and speed zone reductions are expected. Motorists should expect delays.
----------------------------------------
Wood County
This week, crews are scheduled to repair and overlay on FM 852 west between SH 11 and the Hopkins County line. Expect lane closures with flaggers controlling traffic. Crews are also scheduled to repair and overlay on FM 312 between FM 2088 and FM 515.
Wood County construction projects updates:
US 69 Hot mix Overlay
This project consists of milling, level-up, surface repair, structures, signs, and pavement markings. Hot mix pavement operations are now underway. Lane closures are expected, and work zone speed reductions are in place. Motorists should expect delays.
US 69 Grade-Separated Interchange
This project consists of grading, base, asphalt, drainage, structures, overpass, signing, and striping. Construction of the cross structures, drainage, and embankment is underway. Lane closures are expected, and work zone speed reductions are in place. Motorists should expect delays.
----------------------------------------
I-20 Total Maintenance Contract