City of Manchester, NH

11/12/2024 | Press release | Distributed by Public on 11/12/2024 07:20

Christian Brook Sewer Separation, Contract 2 Week of November 11 November 15

Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of November 11th through November 15th .

There will be no work on the streets on Monday, November 11th in honor of Veteran's Day. Starting Tuesday:

Crew 1: Will continue installing drainage piping on Ashland Street between Carnegie Street and Webster Street. They will then replace the water main on this block of Ashland St. Ashland Street will be closed to through traffic with detour signage and police details on site to direct traffic around the construction zones.

Crew 2: Will be lowering catch basins and manhole structures on Sagamore, Birchwood, Blodget, Skyview and High Ridge Road in preparation for paving.

Crew 3: Continental Paving will be reclaiming and grading the following streets: Sagamore Street between Belmont Street and Skyview Road, Blodget Street between Skyview Road and Birchwood Street, Birchwood Street and High Ridge Road south of Blodget Street. These streets will then have the binder course of paving placed, followed by raising of the drainage and sewer structures and water gates.

Crew 4: Will complete raising structures on Tory Road between Joe English Lane to the intersection with Red Coat Lane.

If you have any questions, please reach out to the project team.