Start of construction - Monday, July 29
NO BOAT or PADDLE CRAFT LAUNCHING
(boats can be launched at Mendota Park or Marshall Park)
-
End of construction - October 31
-
Pier/dock to be installed - Spring 2025
The planned general construction sequence includes:
-
Install water main on Lake St., working east from Allen Blvd.
-
Install replacement sanitary sewer across Allen Blvd.
-
After safe water is verified in the new Lake St. main, connect temporary service to the east condo building.
-
Install water main south from Century Ave., down Dewey Ct. and across easement area at Century Harbor to connect with Lake St.
-
Install storm sewer at the east end of Lake St.
-
Construct wall and other landscaping at the new lakeshore park.
-
Install new concrete elements (sidewalks, replacement curb).
-
Majority of fine grading for restoration.
-
Pave road - currently planned for mid-October.