Paving Projects (July Update)

Lakeway Public Works crews are continuing to work with a contractor to repave Lakeway Blvd. and Lohmans Crossing Rd. as part of the voter-approved 2022 Lakeway Transportation Bond. Lakeway Drive was completed in mid-July. The remaining projects will likely continue place through late August. Here is what to expect:

Lakeway Drive

Complete

Lakeway Boulevard

Now- August 2, 2024 (estimate)

This project is scheduled to last through the beginning of August. The paving work will take place from Flamingo Blvd to RM 620. There will be single lane closures during the project with flaggers on hand to help direct traffic as necessary. Please be patient with the crews, and expect some minor traffic delays during the project.

Lohmans Crossing Road

July 31-August 13, 2024 (estimate)

This project is scheduled to begin on Wednesday, July 31 and last through roughly Tuesday, Aug. 13, 2024. The paving work will take place from Hurst Creek Road to RM 620. Expect single lane closures and some detours. Flaggers will also be on hand to help direct traffic where necessary.

Please note that timelines could also be pushed due to weather conditions and other unforeseen circumstances. We appreciate your patience during this process as our crews work to make improvements to our transportation network. If you have any questions, feel free to email us at [email protected] or call Lakeway Public Works at (512) 608-9000.