TRAFFIC ALERT: Route W Bridge Over Givins Creek in Webster Co. OPEN to Traffic

Where: Webster County Route W bridge over Givins Creek north of Marshfield

When: As of 10 a.m., Thursday, August 1

Details: The contractor installed new box culverts, along with new pavement, object markers and permanent striping.

This work is part of a three-year project to improve 25 bridges within 15 miles of I-44 across the Southwest District. Of the 25 bridges in the project, known as the I-44 Corridor Bridge Bundle, seven (7) are mainline I-44 bridges, five (5) are I-44 overpass bridges and the remaining bridges are on adjacent routes over various features. Sixteen (16) bridges will be replaced and nine (9) bridges will receive major rehabilitation work. So far, 23 bridges have been completed in this project.

More information about this project can be found on the project website - I-44 Corridor Bridge Bundle.

Project Details:

  • Prime Contractor - The ESS Team
    • Emery Sapp & Sons, Inc. - Columbia
    • Parsons Transportation Group, Inc. - St. Louis
  • Total Project Cost: $43.2 million
  • Contract Completion Date: September 30, 2024

The ESS Team is a partnership of engineering and construction firms that will design and construct the project with oversight by MoDOT and the Federal Highway Administration.


For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest

Follow MoDOT's Southwest District: Facebook | X | Instagram|YouTube