Question for written answer E-001950/2024
to the Commission
Rule 144
Ana Miranda Paz (Verts/ALE)
The Vigo government has announced the extension of a tunnel in the city centre. The tender for the original tunnel was awarded in 2020 for EUR 13.4 million, which rose to EUR 16.6 million in 2023. Despite initially being a two-year project, the tunnel remains unfinished, with completion now slated for 2026 and forecast to cost EUR 20 million, 63 % more than it was first budgeted at.
Submitted: 3.10.2024