UPDATE on Bond Project A

The city of West Lake Hills has been notified by SpawGlass that the excavation of the detention pond will commence tomorrow (Tuesday) August 13 at approximately 8am. This activity is expected to be completed on Wednesday.

Like previous efforts, heavy equipment that was delivered earlier today ahead of schedule will be used to perform the operation of chipping rock to achieve the configuration and depths needed to construct this element of the project.

The utility contractor will also be either rock sawing, milling, or jackhammering their trench alongside the pond excavation but this is expected to be complete before the pond so this should be the last rock chipping that is done in that area.