Illinois Department of Transportation

07/01/2024 | Press release | Distributed by Public on 07/02/2024 14:25

Rebuilding Rockford: Interstate projects highlight another historic construction season

Gov. Pritzker's capital program modernizing infrastructure throughout region and Illinois

ROCKFORD - Entering one of its busiest construction seasons ever, the Illinois Department of Transportation announced today that major projects in the Rockford area are planned or underway, fueled by Gov. JB Pritzker's historic, bipartisan Rebuild Illinois capital program. Thirteen major projects combined represent a total investment of more than $292 million, improving safety and mobility while sustaining and creating good-paying jobs throughout the region.

"Rebuild Illinois is revitalizing communities and neighborhoods by investing in projects and people in the Rockford area and throughout the state," said Gov. Pritzker. "Through the largest capital program in state history, IDOT will be delivering improvements to build a more resilient, accessible and equitable system of transportation for generations to come, while creating jobs and enhancing local quality of life."

Of the 13 major projects in the Rockford area, six are scheduled to be completed in 2024, and seven are anticipated to be completed between 2025 and 2028.

  • Illinois 2 over the Rock River replacement of the twin bridges is underway with the southbound span, followed by the northbound bridge when completed. One lane will be open in each direction at all times during the project, which will wrap up in 2026.
  • Interstate 39 and U.S. 20 interchange reconstructioncontinues through 2024 with the replacement of the Mulford Road bridge. Additional work includes construction of the new northbound and southbound I-39 lanes and reconstruction of U.S. 20. Traffic includes lane shifts and lane closures. The Mulford Road bridge is expected to reopen in September. The project is expected to be completed by the end of the year.
  • I-39 at Harrison Avenue interchange conversion from a cloverleaf to a modern, safer diverging-diamond design. Other improvements include reconstructing the intersection at Harrison Avenue and Mall Drive, additional lanes, a new multipurpose trail, lighting, traffic signal replacement and culvert replacement. The project is expected to be completed by the end of 2025.
  • Illinois 2 (South Main Street) from Clifton Avenue to Pond Street resurfacing is underway. The project will be completed in August. Expect daily lane closures.
  • Illinois 173 from Lyford Road to Boone County line. Work will resurface the road which will begin this summer and is scheduled to be completed this fall. Expect daily lane closures controlled by flaggers.
  • Illinois 2 near Byron and Illinois 70 in Winnebago County repairs to two bridges are underway: Illinois 2 over Mill Creek south of Byron and Illinois 70 over a drainage ditch east of Leech Road and south of Durand. The Illinois 70 began in June, progressing to the Illinois 2. The project wraps up in August.
  • Illinois 75 from Moate Road to Meridian Road patching and resurfacing begins this summer. Expect daily lane closures controlled by flaggers. Work is expected to wrap up in the fall.
  • I-39 over the Kishwaukee River bridge washing. Work will begin in August and finish in September. Expect daily lane closures.
  • I-39/U.S. 20 to Harrison Avenue expansion to six lanes with an accessory lane. The project also will replace several bridges. Anticipated to begin in 2025 and wrap up by the end of 2027.
  • U.S. 20 from Mill Road to the Kishwaukee River expanding to six lanes, improving the intersection with Mill Road and replacing the bridges crossing the Kishwaukee River. Work is expected to begin in 2025 and conclude in 2026.
  • Springfield Avenue over North Fork of Kent Creek bridge replacement is programmed to start in 2025.
  • Illinois 70 (Kilburn Avenue) from Safford Road to Glenwood Avenue resurfacing is programmed to start in 2025.
  • Baxter Road at I-39 bridge deck overlay is programmed to start in 2025.

Passed in 2019, Rebuild Illinois is investing a total of $33.2 billion over six years into the state's aging transportation system, creating jobs and promoting economic growth. Rebuild Illinois is not only the largest capital program in state history, but also the first that touches all modes of transportation: roads and bridges, transit, waterways, freight and passenger rail, aviation, and bicycle and pedestrian accommodations.

Accomplishments through March 31 of Rebuild Illinois include approximately $14.8 billion of improvements statewide on 6,078 miles of highways, 629 bridges and 895 additional safety improvements. Visit https://idot.click/Rebuild-Illinois for information and highlights of other Rebuild Illinois projects happening throughout the state.

"Under Gov. Pritzker, IDOT continues to deliver projects in the Rockford area that strengthen the state's entire multimodal system of transportation," said Illinois Transportation Secretary Omer Osman. "If you are traveling anywhere in Illinois this construction season, you will be traveling through work zones. Put down the devices. Follow the signs. And when you see orange, slow down and save lives."