10/31/2024 | Press release | Distributed by Public on 10/31/2024 14:05
Anderson County
Palestine crews are scheduled to continue overlay operations on FM 1817. Expect lane closures with flaggers controlling traffic. When complete, crews are planning to blade overlay on FM 2022.
Anderson County construction projects updates:
US 175 Widening Project
The contractor is scheduled to continue working on the new westbound bridge and roadway elements, including pavement and ditch work on the eastbound and westbound sides. Motorists should use caution when traveling through the project. Traffic switch is expected at the north end of the project. Expect lane closures and delays. The speed limit is reduced throughout the project limits. Project consists of expansion to a four-lane roadway with new bridges across the Neches River.
US 79 Truck Parking Area
The contractor will be addressing punch list items pertaining to electrical service. Operations will be in the right of way, but motorists should use caution when traveling through the area. The project includes concrete curb and gutter, earthwork, and drainage improvements.
Gus Engeling Texas Parks and Wildlife
The contractor is awaiting final acceptance. Operations are off public roadways. The project includes surface treatment, pavement striping, and drainage improvements.
----------------------------------------
Cherokee County
Jacksonville and Rusk crews will be cleaning ditches on various roads throughout the county. Expect lane closures with flaggers controlling traffic. There will also be a sweeper truck sweeping roads throughout the county.
Cherokee County construction projects updates:
SH 204
The contractor is scheduled to continue laying hot mix for roadway widening on the west end of the project. The contractor will also place topsoil, permanent seeding, and reinstall SW3P where hot mix operations have been completed. Crews are also scheduled to continue bridge class culvert extensions, grading, and stump removal. Traffic delays are expected due to lane closures. The project consists of adding a super-two highway section.
US 175 Widening Project
The contractor is working on the westbound roadway elements behind the traffic barrier. The east end of the CR 3407 (Dip Rd.) intersection closure began on Monday, Oct. 28. Motorists are encouraged to use the west end of CR 3407 for access to US 175. The contractor will be working on bridge deck pours during nighttime operations. The contractor will also continue clearing utility items. Motorists should be aware of large dirt-moving equipment in the construction zone as well as the traffic switch. The speed limit is reduced to 55 mph throughout the project limits. This project consists of expansion of US 175 to a four-lane roadway with new bridges, grading, hot mix application, drainage structures, pavement markings, and signage.
----------------------------------------
Gregg County
This week, Longview Maintenance is scheduled to continue mill and inlay operations on SH 300, from FM 2275 to the Upshur County line. Expect closures in the north and southbound lanes throughout the week. Traffic will be controlled by flaggers and a pilot car. Crews are also scheduled to begin mill and inlay operations on FM 2275 from SH 300 to US 259. Expect lane closures with flaggers controlling traffic.
Gregg County construction projects updates:
SH 135 - Kilgore Traffic Circle
This project consists of completely rebuilding the traffic circle and full width of roadway to the Rusk County line. Crews will be demolishing the west half of the road. It will consist of removing existing concrete paving, reconstructing subgrade, constructing concrete paving, storm sewer installation, lighting, and striping. The roadway is now open to two-way traffic, south of the traffic circle. The contractor is working on storm sewer and paving at the traffic circle.
SH 149
This project consists of replacing culverts, adding safety end treatments, guard fence, milling and inlaying hot mix asphalt surface, and striping. Contractor crews are scheduled to place rumble strips on lanes and work on the punch list.
FM 2206/Harrison Road Phase 1
This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, flexible base, curb and gutter, sidewalks, hot mix, and pavement markings. Contractor will be installing curb and gutter, driveways, and sidewalk, inlet tops, and possible hot mix asphalt work.
FM 2206/Harrison Road Phase 2
This project consists of widening a two-lane road to four lanes with a center turn lane. This includes drainage structures, new bridge, flexible base, hot mix, and pavement markings. Contractor will be working on the project punch list.
High Street Bridge over UP Railroad
The project consists of replacing the High Street bridge structure over the UP railroad. High Street will be reduced to two lanes - one northbound lane and one southbound lane. One half of the bridge will be constructed at a time. Crews will be working on the retaining walls and construction of the new bridge structure. Expect delays.
----------------------------------------
Henderson County
This week, Athens Maintenance crews will perform base repair on FM 314. Expect lane closures with flaggers controlling traffic on both projects. Crews will also perform herbicide application and sweeping throughout the county.
Henderson County construction projects updates:
SH 198 Bridge Project
The contractor is awaiting final vegetation establishment. Motorists should be prepared for lane closures and delays. The speed limit has been reduced to 50 mph throughout the project. The project consists of the construction of replacing bridges, approaches, grading, structures, base and surface, retaining walls, curb & gutter, metal beam guard fence (MBGF), and pavement markings.
FM 316 Rehabilitation
The contractor is working on punch list items and awaiting final vegetation establishment. Motorists should use caution when traveling through the project and expect lane closures and delays. The project includes pavement reconstruction, structures, pavement markings and signs.
FM 315 Rehabilitation
The contractor is working on punch list items. Contractor is also planning cleanup operations on the Clear Creek bridge. Motorists should use caution when traveling through the project and expect lane closures with delays. The project includes pavement reconstruction, structures, pavement markings and signs.
BUS 19 Sidewalks
The contractor is planning to continue work this week. Motorists should use caution when traveling through the project and expect lane closures and delays when construction begins on Nov. 4. This project includes sidewalk and pedestrian lane improvements.
----------------------------------------
Rusk County
Henderson crews will repair edges on FM 13 and FM 1798. Expect lane closures with flaggers controlling traffic. Expect lane closures with a pilot car and flaggers controlling traffic.
Rusk County construction projects updates:
US 84 - FM 225 East to CR 3155
This project consists of reconstructing US 84, extended structures, hot mix asphalt surface, new signs, and striping. Crews will be extending cross culverts. Motorists should expect delays.
FM 3231 - Subgrade and Seal coat
This project consists of reconstructing FM 3231 completely. Work includes widening and re-laying subgrade, flex base material, and seal coat. Driveway culverts will be upgraded along with new signs and striping. The contractor is scheduled to process the base material in the main lanes. Expect lane closures with flaggers and a pilot car controlling traffic.
SH 315
This project consists of widening pavement edges and installing a four-foot space between the traffic lanes to separate opposing traffic for safety. Work will also include adding a passing lane in each direction of travel. The entire surface will be milled, and new hot mix will be placed for the final surface. Project also includes replacing some driveway pipes, metal beam guard fence, and striping. No work is scheduled this week.
FM 2658
This project consists of reconstructing FM 2658 completely, from CR 344 to FM 1251. Work includes guard fence, treating subgrade, flex base material, seal coat, and striping. The contractor is scheduled to mill off old asphalt and mix subgrade on the south end of the project. This will be a one lane setup with flaggers and a pilot car controlling traffic.
US 79 Rehabilitation
This project consists of rehabilitation of US 79 consisting of pavement repair, seal coat, asphalt PFC surface, driveway culverts, and pavement markings. This week, the contractor is scheduled to install driveway culverts and clearing the right of way. Motorists should expect delays with flaggers controlling traffic.
US 79 N
This project consists of repairing slope failure in the TxDOT right of way. The site will be excavated, and a new embankment will be placed. This week, the contractor will be excavating the embankment. Most of the work will be off of the roadway. Motorists should expect shoulder closures and trucks entering the highway.
----------------------------------------
Smith County
This week, Tyler Maintenance will continue mill and inlay on FM 14 from I-20 to FM 16 in the north and southbound lanes. When complete, crews are scheduled to begin seal coat prep on FM 2607.
A second crew will be performing bridge maintenance on FM 1995 and FM 344. Expect lane closures with flaggers controlling traffic. There will also be a patch crew working at various locations throughout the county.
Smith County construction projects updates:
Tyler State Park Bridge and Resurfacing Project
The contractor is scheduled to complete the installation of the concrete flume with riprap stone at the roadway runoff points. When complete, the contractor will then remove erosion control. This project consists of the construction of a new bridge and parking areas.
US 69 Rehab Existing Road and Restricted Crossing U-Turn (R-Cut)
The contractor has no work scheduled this week. This project consists of rehabilitating existing roadway and installing a restricted crossing U-turn (R-Cut) at FM 2813 intersection.
US 69/SH 31 Safety Improvement
The contractor is scheduled to install the mow strip in the medians along US 69. Lane closures are anticipated. The project consists of safety improvements consisting of the installation of a median cable barrier.
SL 323 Overlay on Existing Roadway
The contractor is scheduled to perform permanent striping. Nightly lane closures are anticipated. This project consists of overlaying existing roadway with permeated friction course (PFC) asphalt.
I-20 Frontage Road at SH 155
The contractor is scheduled to remove and replace problem areas. No delays are expected. Project consists of resurfacing the roadway, pavement markings, signage, and illumination.
I-20 Mill and Inlay
The contractor has no work scheduled this week. Project consists of an overlay with TBPFC surface, ACP surface, planing, shoulder texturing and pavement markings.
Legacy Trails Extension
The contractor is scheduled to resume pouring concrete for the parking lot in Stewart Park. No lane closures are anticipated. This project consists of a hike and bike trail development that includes construction of a 12-foot wide shared-use paths.
FM 2493 Widen Non-Freeway
The contractor has no work scheduled this week. No lane closures are in place. The project consists of widening the existing roadway.
County Bridge Replacements
The contractor is scheduled to demolish the Mill Creek bridge on CR 452 and begin installation of the drill shafts. The bridge will be closed for the duration of construction. Project consists of replacing the existing bridges and approaches.
SH 110 Preventative Maintenance
The contractor has no work scheduled this week. No lane closures are anticipated. The project consists of preventative maintenance that includes surface overlay and pavement markings.
SH 110 Traffic Signals
The contractor has no work scheduled this week. This project consists of adding traffic signals to SH 110 and Loop 49 ramps and overlay operations.
I-20 Mill and Inlay at SH 135
The contractor is scheduled to clean and seal the bridge joints and cut in the rumble strips. Lane closures are anticipated. Project consists of an overlay with thin-bonded permeable friction course (TBPFC) surface, asphalt concrete pavement, planing, shoulder texturing and pavement markings.
FM 16 Widening and Realignment
The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge, and culvert structures, signing, pavement markings, and signals. Crews will be preparing the right-of-way by removing trees and grading the embankment. Motorists should expect trucks entering and exiting the roadway. Construction of traffic signals are scheduled to begin at the intersection of US 69 and FM 16. Traffic shift detours are in place. Motorists are urged to drive with caution and expect delays.
---------------------------------------
Van Zandt County
Crews are scheduled to perform base repair on FM 90. A second crew will continue to address bridge channel maintenance on various bridges in the county. Expect lane closures with flaggers controlling traffic.
Van Zandt County construction projects updates:
SH 19 Super Two Widening & Overlay (North of US 80)
The project consists of super two work, including grading, base repair, treated subgrade, flex base, OCST, PFC surface, structures, signs, and pavement markings. Major items of work have been completed.
I-20 Frontage Roads West of FM 314 and East of FM 47
This project is for roadway restoration consisting of scarifying, treating existing material & subgrade, flex base, prime coat, TCST, ACP base, ACP surface, metal beam guard fence, structures, signs, and pavement markings. Work is in progress west of FM 314 and east of FM 47. Major items of work have been completed.
CR 1102 Bridge Replacement
This project is for the construction of a bridge replacement consisting of replacing bridge and approaches, grading, ACP base and surface, and metal beam guard fence installation. Major items of work have been completed.
FM 17, FM 47, and FM 859 Bridge Replacement
This project is for the construction of a new bridge and approaches, grading, ACP base, and surface, and metal beam guard fence installation. The project will begin with the replacement of FM 859 & FM 47 bridges the last week of November. Motorists should expect work zone speed limit reductions and shoulder width reductions on the I-20 main lanes. Motorists should also expect work zone speed limit reductions and shoulder width reductions on the I-20 frontage roads. The bridge at FM 859 is closed and detours are in place. Motorists should pay attention and travel with caution in the work zone. The bridge at FM 17 will have a new traffic sequence with four-way stop conditions at both intersections of FM 17 and the I-20 frontage roads. Motorists should pay attention and travel with caution throughout the work zone.
FM 1255 Rehabilitate Existing Roadway
This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, rework base material, cement treatment, flex base, TCST, resurfacing intersections & driveways, extending cross structures, signs, and pavement markings. The project will be completed under traffic. Subgrade rehabilitation will be completed in one-mile segments. Construction is on-going for the pavement rehabilitation, cross structures, and right of way clearing. Lane closures and speed zone reductions are expected. Motorists should expect delays.
SH 64 at I-20 and SH 155 at I-20 Traffic Signal Install
This project is for the construction and installation of traffic control devices including pedestrian signals. On SH 64, crews are currently working on driveways, drainage structures, signals, and roadway widening. Crews are preparing to restripe the intersections at SH 64 and SH 155. Lane closures and speed zone reductions are expected. Motorists should expect delays.
SH 243 Traffic Signal Install
This project is for the construction and installation of traffic control devices including pedestrian signals. Major items of work have been completed.
I-20 WB Exit Ramp at SH 19
This project consists of ramp improvements. Crews have initiated construction on the drainage structures and frontage road alignment. Crews are also hauling in large amounts of dirt. Lane closures and traffic shifts are expected. Motorists should expect delays.
FM 1651 Rehabilitate Existing Roadway
Construction is on-going for cross structures, driveways, and right of way clearing. Lane closures and speed zone reductions are expected. Motorists should expect delays.
This project is for the rehabilitation of the existing roadway consisting of roadway widening, grading, rework base material, cement treat, flex base, OCST, resurfacing intersections & driveways, extending cross structures, signs, and pavement markings. The project will be completed under traffic. Subgrade rehabilitation will be completed in approximate one-mile segments.
----------------------------------------
Wood County
This week, crews are scheduled to continue base repair on FM 1647 between SH 11 and FM 852. Expect lane closures with flaggers controlling traffic. Also, crews are scheduled to perform edge repair on FM 312 between FM 2088 and FM 515. Expect lane closures with flaggers controlling traffic.
Wood County construction projects updates:
US 69 Hot mix Overlay
This project consists of milling, level-up, HMA surface, structures, signs, and pavement markings. Hot mix pavement operations are now underway. Lane closures are expected, and work zone speed reductions are in place. Motorists should expect delays.
US 69 Grade-Separated Interchange
This project consists of grading, base, asphalt, drainage, structures, overpass, signing, SW3P, and pavement markings. Construction of the cross structures, drainage, and embankment is underway. Lane closures are expected, and work zone speed reductions are in place. Motorists should expect delays.
----------------------------------------
I-20 Total Maintenance Contract