10/28/2024 | Press release | Distributed by Public on 10/28/2024 02:53
The audit was conducted from 2 to 5 September 2024.
The objective of the audit was to verify that Equinor's management of materials handling, lifting operations, personnel transfer and emergency preparedness using service operation vessels (SOVs) at the unmanned Oseberg H installation complied with the regulatory requirements as well as the company's own requirements. A further objective was to monitor how Equinor has followed up and worked systematically to prevent accidents.
The audit identified two non-conformities, concerning:
We also identified two improvement points, concerning:
We have asked Equinor to report on how the non-conformities will be addressed, and for their assessment of the improvement points observed. The reply deadline is set at 18 November 2024.