Vetropack Holding AG

07/09/2024 | Press release | Archived content

Strategic Energy Management

Strategic Energy Management

09.07.2024:The production of glass packaging is an energy-intensive process that lasts 24 hours a day. Therefore, a constant supply of energy is essential for the production process. The announcement of a 48-hour gas supply interruption to our Hum na Sutli plant in June 2024, due to maintenance work on the main gas pipeline, represented a significant challenge for maintaining the continuity of production.

Implementation of alternative solution

Existing solutions for gas supply interruptions were sufficient to maintain basic functions but were not adequate to maintain full operating capacity in production. Therefore, Vetropack Straža decided on an integrated technical solution that combines synthetic gas (produced by mixing liquefied petroleum gas and air) and natural gas from compressed natural gas tanks, which ensures smooth operation of the entire plant during interruptions.

The gas supply was interrupted in the early hours of 18 June and the interruption lasted for a total of 38 hours, ten hours less than expected.

Watch the video to see how the alternative energy supply process worked during the interruption.

Video

Strategic importance and business excellence

This solution is not only a significant contribution to the sustainability of our business, but also a demonstration of our adaptability. Diversification of energy sources reduces the risks associated with supply interruptions and increases the security of our energy system.

Thanks to a proactive and strategic approach, Vetropack Straža has successfully reduced the business risks associated with energy supply disruptions, confirming its commitment to effective risk management and promoting sustainable practices

Contact persons

Communications Specialist
Maja Starček
maja.starcek@vetropack.com