UPDATE #2: Berryhill Road resurfacing from Pond Creek Bridge to Pine Ridge Drive

The Berryhill Road repaving project from Pond Creek Bridge to Pine Ridge Drive began Tue., July 9. This project has been broken up into phases. Phase onefrom Pond Creek Bridge to the Dollar General (5325 Berryhill Rd.) closest to Anderson Lane is expected to be completed by Fri., July 19.

Phase twoof the project will include repaving Berryhill Road just east of Anderson Lane to Pine Ridge Drive beginning Mon., July 22. This section is expected to be complete within one week.

Phase threewill involve repaving the portion of Berryhill Road at the Anderson Lane intersection (beginning just past the Dollar General) and is expected to begin Mon., July 29. This portion of the project is also expected to be completed within one week. Different materials will be used for this portion and some leveling will take place to help improve safety at the Anderson Lane intersection.

Completion is weather dependent for all phases. Drivers are asked to use caution while workers are present and should expect heavy delays until the project is complete.

Funding for this project comes from the Gas Tax. Find a view of the map online.

# # #