As of October 14th, 2024, Bayo Vista Way and Terradillo Ave Easement have been completed.
The following work is taking place on the following streets:
-
Billou St.: The remaining lateral reconnections will be completed by October 25th, and paving will take place the last week of October.
-
Madrona St: The sewer mainline installation and lateral reconnections will be taking place on October 14th through October 22nd.
-
McCoy Rd: Contractor began potholing and work will be taking place throughout the week of October 14th
-
Grove St: Saw cutting commenced on Oct 14th. The sewer work will begin October 21st