2023 Sewer Improvements- Various Locations

As of October 14th, 2024, Bayo Vista Way and Terradillo Ave Easement have been completed.

The following work is taking place on the following streets:

  1. Billou St.: The remaining lateral reconnections will be completed by October 25th, and paving will take place the last week of October.
  2. Madrona St: The sewer mainline installation and lateral reconnections will be taking place on October 14th through October 22nd.
  3. McCoy Rd: Contractor began potholing and work will be taking place throughout the week of October 14th
  4. Grove St: Saw cutting commenced on Oct 14th. The sewer work will begin October 21st