City’s 2024 Street Resurfacing Program Wrapping Up

City's 2024 Street Resurfacing Program Wrapping Up

SEPTEMBER 24, 2024 - The City's Street Resurfacing Program is wrapping up with crews continuing to work on the sixth and final location for 2024: Apple Valley (4160 Apple Valley Drive to cul-de-sac). Currently, crews are installing storm sewer.

SEPTEMBER 9, 2024 -
The City's Street Resurfacing Program continues with crews continuing to work on the fifth location for 2024: Holmes Street (alley west of 6th Street to 6th Street).

Crews are expected to start working on the sixth and final location later this week (weather permitting): Apple Valley (4160 Apple Valley Drive to cul-de-sac).

AUGUST 29, 2024 -
The City's Street Resurfacing Program continues with crews now working on the fifth location for 2024: Holmes Street (alley west of 6th Street to 6th Street). This stretch of road is closed until work is complete, which is expected to take approximately three weeks (weather permitting).

AUGUST 19, 2024 -
The City's Street Resurfacing Program continues with work wrapping up during the week of August 19th on the second and third locations for 2024: Linden Lane from Hillside Drive to Spruce Hills Drive and Tanglewood Road east of Middle Road.

Crews are expected to pave the fourth location on Wednesday, August 21st (weather permitting): Parklane Circle.

Once those three locations are complete, crews will move onto the fifth location for 2024: Holmes Street (alley west of 6th Street to 6th Street). Work is expected in that area later this week with the sixth and final location - Apple Valley Drive (4160 Apple Valley Drive to cul-de-sac) - projected to be under construction the week of August 26th.

AUGUST 7, 2024 -
The City's Street Resurfacing Program is progressing with work continuing on the second of five locations: Linden Lane from Hillside Drive to Spruce Hills Drive. The last step - the paving process - is expected to take place sometime during the week of August 12th, weather permitting.

Crews are also beginning grading operations at the third of five locations: Tanglewood Road east of Middle Road. The paving process is expected to take place by August 9th, weather permitting.

The City also added a sixth location to its 2024 Street Resurfacing Program due to its deteriorating condition: Parklane Circle. Crews started milling operations this week and plan to complete the paving process by August 9th, weather permitting.

JULY 17, 2024 - The City's Street Resurfacing Program has moved to its second of five locations: Linden Lane from Hillside Drive to Spruce Hills Drive. Resurfacing at this location is expected to take approximately two weeks, weather permitting.

During the week of July 22, 2024, the third of five locations will go under construction: Tanglewood Road east of Middle Road. Resurfacing at this location is expected to take approximately two weeks, weather permitting.

MAY 9, 2024 -
Beginning Monday, May 13, 2024, the City of Bettendorf's 2024 Street Resurfacing Program gets underway with its first of five locations scheduled for the year:

In Alphabetical Order

  • Apple Valley Drive (4160 Apple Valley Drive to cul-de-sac)
  • Holmes Street (alley west of 6th Street to 6th Street)
  • Linden Lane (Hillside Drive to Spruce Hills Drive)
  • Tanglewood Road (East of Middle Road)
  • Weindruch Road (State Street to Devils Glen Park)

"This annual program is part of the City's Pavement Management Program, which started in 2015," said Brent Morlok, City Engineer. "Our street network is one of the City's most important assets, and one that we invest in heavily to ensure that it remains in good working condition for the public. Our Pavement Management Program helps us make objective decisions on how to best allocate Capital Improvement Funding."

To learn more about the City's Pavement Management Program, click here.

The first site to go under construction is Weindruch Road from State Street to Devils Glen Park on May 13. Resurfacing at this location is expected to take approximately four weeks, weather permitting.

To ensure the safety of the traveling public and the construction workers onsite, Weindruch Road will only be open to local traffic during construction and a detour will be in place (see map below). To access Devils Glen Park, use the park entrance on Devils Glen Road.

As construction wraps up at this first site, the contractor in charge of the 2024 Resurfacing Program will choose the next site. The City will post those updates here.

For updates on this project and others across the City of Bettendorf, click here.

Share this page

Share this page

×

Copy and paste this code into your website.

Your Link Name

Share this page on your favorite Social network

Close
Please ensure Javascript is enabled for purposes of website accessibility