Annual Pavement Rehabilitation Project - Updated Work Schedule

The City of Buena Park is continuing to work on the 23-24 Annual Pavement Rehabilitation Project. The project will include removing and replacing street pavement, sidewalks, curbs and gutters, cross gutters, curb ramps, striping, and traffic loops in several areas in the City. The below table indicates the tentative days of work on each project street. Dates are subject to change, and any changes to the schedule will be reflected on this website page until the end of construction.

Date

Streets Affected

Work Schedule

Parking Notes

7/30/2024

Academy Dr
Campus Dr
Faculty Cir

Street Grinding

During Work - No parking/driving where marked
After Work - Driving Allowed

7/31/2024

Rostrata Ave
Kingman Ave - From Artesia Ave to Franklin St

Street Grinding

During Work - No parking/driving where marked
After Work - Driving Allowed

8/1/2024

Burnham Ave
Fullerton Ave

Street Grinding

During Work - No parking/driving where marked
After Work - Driving Allowed

8/2/2024

Western Ave
Kingman Ave - From Franklin St to cul-de-sac

Street Grinding

During Work - No parking/driving where marked
After Work - Driving Allowed