Christian Brook Sewer Separation, Contract 2 Week of July 29 August 2

Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of July 29th through August 2nd .

Crew 1: Park Construction will continue replacement of the water main and installation of the new 18" drain piping on Webster Street. Webster Street will be closed to all traffic between Maple Street and Tory Road during this work. Traffic detour signage will be in place to re-route traffic around the construction zone and police details will be on site to direct traffic. The contractor will also replace the existing water main and continue installation of new catch basins and piping on Oak Street north of Webster Street. Oak Street will be closed to through traffic between Webster Street and Red Coat Lane with detour signage and police details to direct traffic around the construction zones.

Crew 2: Will continue installation of the 24" drain line on Belmont Street between Smyth Road and Sagamore Street. Belmont Street will be closed to through traffic with detour signage and police details to direct traffic around the construction zone.

If you have any questions, please reach out to the project team.