12/03/2024 | Press release | Distributed by Public on 12/03/2024 12:45
Park Construction Corporation will continue construction activities on the Christian Brook Sewer Separation project during the week of December 2nd through December 6th.
Crew 1: Will continue installation of drain and sewer piping on Belmont Street between Carnegie Street and Webster Street.
Crew 2: Northeast Roads will be raising catch basins and manhole structures on recently paved streets including Tory Road, Joe English Lane, Red Coat Lane, and Carnegie Street then pave around the structures.
Crew 3: Tri-State Curb will continue replacement of granite curbing on Oak Street and Salmon Street.