MoDOT - Missouri Department of Transportation

11/06/2024 | Press release | Distributed by Public on 11/06/2024 09:42

MoDOT TRAFFIC ALERT: U.S. Route 65 J-Turn at Bluegrass Road (Farm Road 94) OPEN

North of Springfield Monday, November 11

Where: U.S. Route 65 J-Turn at Bluegrass Road (Farm Road 94) OPEN North of Springfield

When: Monday, November 11

What: Contractor crews have open the J-turn on U.S. Route 65 at Bluegrass Road (Farm Road 9) north of Springfield. To finish the project, crews will CLOSE the crossover at Route 65 & Bluegrass Road and the Route 65 north and southbound left turn lanes for up to one week beginning November 11.

Traffic Impacts:

  • U.S. Route 65 J-Turn at Bluegrass Road (Farm Road 94) OPEN North of Springfield
  • Crossover median Closed at Route 65 and Bluegrass Road (Farm Road 94) for up to one week beginning November 11
  • North and southbound Route 65 left turn lanes Closed to Bluegrass Road (Farm Road 94) for up to one week beginning November 11
  • Route 65 and Bluegrass Road (Farm Road 94) Open
  • Signs and message boards will alert drivers approaching the work zone
  • Drivers will need to follow the signed detour or seek an alternate route to avoid the work zone
  • Check MoDOT's Traveler Information Map for road closings/traffic impacts

Weather and/or construction delays will alter the work schedule.

Project information

  • Contractor: Emery Sapp & Sons, Inc. - Columbia
  • Completion date: December 1, 2024
  • Estimated total cost: $2.1 million

END

For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest