As part of the Bucknam Road Bridge Replacement Project, MaineDOT will close Bucknam Road between the I-295 Southbound and Northbound intersections overnight from Monday, May 6 through Thursday, May 9 and Sunday, May 12 through Thursday, May 16 between 10:00pm and 5:00am. In addition, during this same time period, there will be intermittent closures of I-295 Northbound and Southbound ramps at Exit 10 between 10:00pm and 5:00am.
Motorists will be directed to utilize a signed detour route via various message boards and signage. Below is the tentative schedule of these closures. Note: These schedules are weather dependent.
Bucknam Rd. & Exit 10 On/Off Ramp Closure Schedule
Note: All Closures between 10:00 pm and 5:00 am
Day |
Date |
Bucknam Rd. |
I-295 SB On/Off Ramps |
I-295 NB On/Off Ramps |
Monday |
May 6 |
CLOSED |
||
Tuesday |
May 7 |
CLOSED |
||
Wednesday | May 8 | CLOSED | ||
Thursday |
May 9 |
CLOSED |
||
Sunday |
May 12 |
CLOSED |
CLOSED |
|
Monday |
May 13 |
CLOSED |
CLOSED |
|
Tuesday |
May 14 |
CLOSED |
CLOSED |
|
Wednesday |
May 15 |
CLOSED |
CLOSED |
|
Thursday |
May 16 |
CLOSED |
CLOSED |
Additional information on MaineDOT's Bucknam and Johnson Road Bridge replacement projects can be found on our project page at: https://www.falmouthme.org/bucknam-road-bridge-replacement-project and at MaineDOT's project page at: https://www.maine.gov/mdot/projects/falmouth/johnsonrd/