Pennsylvania Department of Transportation

05/08/2024 | Press release | Distributed by Public on 05/08/2024 14:14

Route 51 Ramp to Northbound I-79 10-day Closure Begins Friday in Robinson Township

Route 51 Ramp to Northbound I-79 10-day Closure Begins Friday in Robinson Township

05/08/2024

​Pittsburgh, PA - PennDOT District 11 is announcing the 10-day closure of the ramp carrying traffic from Route 51 (Coraopolis Road) to northbound I-79 in Robinson Township, Allegheny County will begin, Friday, May 10 through Tuesday, May 21 weather permitting.

The ramp carrying traffic from Route 51 to northbound I-79 will close to traffic from 7 p.m. Friday night through 6 a.m. Tuesday, May 21 to allow crews to conduct ramp reconstruction work. Ramp traffic will be detoured. Please use caution when traveling through the work zone.

Posted Detour

  • From the closed ramp, head north on Route 51

  • Turn right and cross the Coraopolis Bridge

  • Continue along Grand Avenue

  • Take the ramp to northbound I-79 toward Erie

  • End Detour

This work is part of the $43.9 million I-79 "S-Bend" Project that includes full-depth pavement reconstruction, bridge preservation work on five mainline structures (I-79 northbound and southbound over Clever Road, I-79 northbound and southbound over Route 51, and the Neville Island Bridge). Additionally, there will be milling and paving of three ramps at the Route 51 (Coraopolis/McKees Rocks) interchange. The project also includes guiderail replacement, highway lighting and signing upgrades, new pavement markings and delineation, and other miscellaneous construction work.

Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras.

511PA is also available through a smartphone application for iPhone and Android devices

Contact: Nicole Haney, 412-429-5011

# # #